Installation of NE-type Bucket Elevator
Author :

The NE series bucket elevator is a vertical type. Its foundation supports the entire weight of the elevator. Therefore, before installation, the foundation must be inspected.
The NE series bucket elevator is generally shipped in several parts and assembled on site. It is usually installed in the following sequence:
- First, install the anchor bolts on the foundation, then install the lower part of the machine. Align its position on the foundation to ensure that the reference surface (upper flange surface) of the casing is horizontal. Then temporarily secure it to the foundation.
- Install the middle casings one by one on the lower part of the machine. Generally, the middle section with the inspection door is installed in the position of the first middle casing. The first middle casing must be connected to the upper part of the machine (note the direction of the support of the first middle casing).
- After the middle casings are installed and aligned, install the upper part of the machine. Generally, support devices should be installed at the upper and middle positions to prevent the casing from shifting sideways. The support devices should be securely fixed to the nearby building and allow the elevator to expand and contract freely in the vertical direction. Coarse canvas or woven asbestos tape and asbestos rope should be placed at each flange connection to prevent dust from escaping.
- Install the drive unit on the upper part of the machine. First, connect the three pieces of the platform into a whole with bolts. Then connect the whole platform and eight support channels to the upper casing with bolts or welding. Weld the maintenance frame and segmented guardrails to the whole platform. Then install the power unit, chain drive, and chain wheel cover. After the chain drive is adjusted, fix the bolts. For safety, weld the drive base and the moving platform together.
- Install the running parts. First, lift the tail shaft to the highest position, then install the chain and buckets.
- Finally, install the left and right head covers, set up the electrical overload protection device and electrical protection switch, and install the power line on the motor of the elevator.
NE-type Bucket Elevator,bucket elevator
Previous page
Previous page
Get a Free Quote
We sincerely welcome you to write to us, call us to inquire about our business, visit us, inspect us, buy us and adopt us. You have any questions you can write to call, you can also leave a message on this site, the site administrator will do our best to provide you with the most efficient service.
HOT NEWS
Customer Service Hotline
Add:No. 8, Changjiang Road East, Lucheng Street, Yidu City, Hubei Province
Tel:+86-717-4904858 / 4820569
Mr. Zhou:+86-15871569828
Mr. Gong:+86-13508601368
Ms. Zou:+86-13872614986
© COPYRIGHT HUBEI YIDU YIYUN MEC.&ELEC. ENGINEERING CO.,LTD ALL RIGHTS RESERVED | Power by 300.cn
SAF Coolest v1.3.1.2 设置面板 GAGSD-ZGYF-JVZFE-ZVF
无数据提示
Sorry, the current section is being updated, so stay tuned!
You can view other columns or return to Home