Part 2: Installation Process and Precautions for Overflow Screw Conveyor -- Post-Installation Commissioning & Key Installation Taboos and Risk Alerts

Author :


Continuing from the previous blog < Part 1: Installation Process and Precautions for Overflow Screw Conveyor -- Pre - Installation Preparation & Core Component Installation >

 

IIIPost-Installation Commissioning

After installationthe equipment must undergo no-load and load commissioning to ensure normal operation.

1No-Load Commissioning (CoreCheck Operational Stability)

Process Steps

  1. • Inspect ConnectionsTighten all bolts again (especially the bearing housing and drive unit anchor boltsand confirm that the seals are not loose.
  2. • Manual RotationRotate the screw shaft 2-3 turns manually to ensure there is no jamming or abnormal noiseand that the bearings rotate smoothly.
  3. • Power - On Test Run

• Spot Test the MotorRun the motor intermittently (for 10-15 seconds each timeto observe whether the rotation direction of the screw shaft is consistent with the designed conveying direction (if reversedadjust the motor wiring).

• Continuous No-Load OperationRun continuously for 1-2 hours under no-load conditionsDuring this periodcheck the following

• Bearing TemperatureShould be ≤70°C (measured with an infrared thermometer).

• Motor CurrentShould not exceed 60% of the rated current.

• Equipment NoiseShould be ≤85dB (measured with a sound level meter).

• If the bearings overheat (exceeding 70°C)check whether the lubricating grease is sufficient or if the bearings are installed too tightlyIf the noise is too highcheck the coaxiality of the coupling or the gap between the screw shaft and the casing.

Precautions

  1. • During no-load commissioningpersonnel are prohibited from approaching the ends of the screw conveyor and the inlet to prevent accidental entanglement.
  2. • If any abnormalities occur during commissioning (such as motor tripping or abnormal noise)the power must be immediately cut off and the machine stoppedTroubleshoot the problem before re-commissioningDo not force the machine to run.

 

2Load Commissioning (CoreVerify Conveying Efficiency and Sealing)

Process Steps

  1. • Gradual FeedingStart by feeding at 30%of the designed conveying capacity and run for 30 minutes to observe whether the material is conveyed smoothly and whether there is any accumulation at the discharge portIf normalgradually increase to 50%80%and 100% of the designed capacityrunning for 1 hour at each load level.
  2. • Check Key Indicators

• Conveying EfficiencyMeasure the actual conveying capacity by weighingwith the deviation from the designed value being ≤±5%.

• SealingCheck for material leakage at the casing flangeshopperdischarge portand shaft end sealsIf leakage is foundadjust the tightness of the seals or replace the gaskets.

• Motor LoadDuring full-load operationthe motor current should not exceed the rated currentOtherwisecheck for material blockages or screw shaft jams.

Precautions

  1. • During load commissioninga dedicated person must monitor the equipment’s operating conditionespecially the inlet and discharge portsto prevent material blockages (if blockedstop the machine immediatelyclear the materialand then resume operationDo not run with blockages).
  2. • If conveying materials that easily generate dustthe dust collection device must be activated to ensure that the dust concentration in the working environment meets national standards (e.g.≤10mg/m³).

 

IVKey Installation Taboos and Risk Alerts

  1. • Prohibit Forced InstallationWhen components are deformed (such as bent screw blades or misaligned casing flanges)they must not be forcibly connectedComponents should be corrected or replaced firstOtherwiseit will lead to increased component wear during operation and may even cause equipment failure.
  2. • Avoid Lubrication OmissionsMoving parts such as bearings and reducers must be lubricated with grease/ oil according to the manual requirementsand the type and amount must be accurate (for exampledo not overfill the reducer with lubricating oilas this can cause oil temperature to rise and oil leakage).
  3. • Emphasize Electrical SafetyThe grounding and wiring of the drive unit must comply with electrical standardsUnauthorized personnel are strictly prohibited from wiringBefore commissioningensure that the supply voltage matches the motor’s rated voltage (e.g.380V/220Vto prevent motor burnout.
  4. • Special Requirements for Inclined InstallationIf the conveyor is inclined (the inclination angle is usually ≤20°depending on the equipment model)an “anti - backflow baffle” must be installed at the bottom of the casing to prevent material backflow due to gravityAt the same timethe power of the drive unit needs to be increased (the power for inclined installation should be 10% - 20%higher than that for horizontal installation).

 

By strictly following the above installation procedures and precautionsthe installation quality of the overflow screw conveyor can be maximizedreducing subsequent operational failures and extending the service life of the equipmentIf complex problems are encountered during installation (such as deflection control of large - span conveyors or sealing design for special materials)it is recommended to consult the equipment manufacturer’s technical personnel for targeted guidance.

Overflow Screw Conveyor,Trough Screw Conveyor,screw conveyor,Installation Process

Get a Free Quote

We sincerely welcome you to write to us, call us to inquire about our business, visit us, inspect us, buy us and adopt us. You have any questions you can write to call, you can also leave a message on this site, the site administrator will do our best to provide you with the most efficient service.