Installation Instructions for En-Masse Conveyor
Author :
The installation of the en-masse conveyor must follow specific steps and requirements to ensure the normal operation and service life of the equipment. Here is a detailed installation guide:
Pre-Installation Preparation
- Check and Inventory Components: According to the packing list provided by the manufacturer, count, classify, and inspect all components of the conveyor. Store them properly to avoid rust and corrosion caused by outdoor storage.
- Check Dimensions: Carefully check the dimensions of all conveyor casings, foundations, and brackets. Resolve any issues promptly.
- Prepare Tools: Prepare necessary installation tools such as wrenches, electric welders, acetylene cutting machines, steel wire ropes, and thin steel wires.
- Arrange Personnel: Assign skilled installers, including fitters, welders, riggers, and electricians.
Casing Installation
- Fix Brackets: During installation, first use a level to confirm the levelness of the foundation and brackets, then spot-weld the brackets to fix them.
- Install in Sequence: Install conveyor components in sequence starting from the head section as required by the installation layout drawing. Ensure the levelness and verticality of the conveyor casing, especially that the butt joints of the bottom plates are flush. The allowable downward error along the running direction is 0.5-1mm. Avoid left-right misalignment of the side plates to ensure the smooth operation of the scraper chain.
- Calibrate Straightness: After all conveyor casings are assembled, their straightness must meet the requirements. For conveyors with a total length less than 30m, the straightness should not exceed 5mm; for those longer than 30m, the straightness should not exceed 8mm. If not, calibration is necessary.
- Fix the Casing: The head section must be firmly installed on the foundation or bracket. The middle and tail sections should be fixed with locking blocks to prevent the conveyor from swinging during operation. If the temperature of the conveyed material exceeds 200°C, an expansion joint should be installed at the feed inlet, and the middle and tail sections must not be fully welded to the bracket.
- Align Head and Tail Sections: The head and tail sections must be aligned during installation. The axes of the two sprockets should remain parallel to prevent the scraper chain from deviating during operation.
Scraper Chain Installation
- Inspect the Chain: Before installation, check whether the joints of the scraper chain are flexible. If they are not, disassemble them and polish the pin shafts and chain rod holes with sandpaper to ensure flexibility. Do not apply lubricating oil or grease.
- Determine Chain Direction: Before installing the scraper chain, open the head and tail end covers and observation covers, adjust the tail shaft to the foremost position towards the head, and determine the direction of the scraper chain. The head wheel teeth should drive the large end of the chain rod of the scraper chain to move forward; reverse installation is strictly prohibited.
- Install the Chain: Determine the installation method based on the conveyor length and on-site conditions. Generally, install the lower scraper chain first, then the upper scraper chain, with the upper and lower chains in opposite directions.
- Connect the Chain: Connect the upper and lower scraper chains at the head, then pull the chain at the tail to tighten it. After reaching the appropriate length, complete the connection at the tail. Note that when connecting the scraper chain, the elastic retaining rings must be clamped tightly or the pin shaft retaining rings must be welded firmly.
Drive Device Installation
Feed Inlet Installation
Chain Tensioning
Inspection and Idle Operation
En-masse conveyor,chain,flight,Bulk material
Get a Free Quote
We sincerely welcome you to write to us, call us to inquire about our business, visit us, inspect us, buy us and adopt us. You have any questions you can write to call, you can also leave a message on this site, the site administrator will do our best to provide you with the most efficient service.
HOT NEWS

Customer Service Hotline
Add:No. 8, Changjiang Road East, Lucheng Street, Yidu City, Hubei Province
Tel:+86-717-4904858 / 4820569
Mr. Zhou:+86-15871569828
Mr. Gong:+86-13508601368
Ms. Zou:+86-13872614986
© COPYRIGHT HUBEI YIDU YIYUN MEC.&ELEC. ENGINEERING CO.,LTD ALL RIGHTS RESERVED | Power by 300.cn
SAF Coolest v1.3.1.2 设置面板 GAGSD-ZGYF-JVZFE-ZVF
无数据提示
Sorry, the current section is being updated, so stay tuned!
You can view other columns or return to Home